Some areas in Lagos State will experience eight weeks of power outage as Ikeja Electric, IE, announces a planned reconductoring of 132kv lines.
The re-conducting will be embarked upon by the Transmission Company of Nigeria, TCN, which is aimed at expanding the wheeling capacity across the IE network.
Kumapayi noted that the outage became necessary because some of the 132Kv lines installed over 50 years ago had become obsolete and degraded due to time and usage.
He said: “The TCN is currently embarking on the upgrade of the 132KV lines from Ikeja West to Ota and Alimosho in stages. This is the second stage.
“We will replace all the aluminium conductors with gap conductors which is more sophisticated to withstand heat and has more capacity to carry current.
“The implication of this is that from 8am to 6pm every day, the substations controlling these areas will be switched off which will affect the feeders connected to them.”